Benefits of Rotational, Thin Layer, Air Dried Tailing Deposition after 25-Years of Operation of the Juniper Tailing Storage Facility

Benefits of Rotational, Thin Layer, Air Dried Tailing Deposition after 25-Years of Operation of the Juniper Tailing Storage Facility

Author: Allen Gipson, Jason Taylor, Joseph Chilson, Brittany Hutchings
Conference: Tailings and Mine Waste 2018
Date: September 30-October 2, 2018

ABSTRACT
From inception in the late 1980s, the Juniper Tailings Storage Facility has been constructed in stages as a massive, compacted, rock fill, modified centerline embankment to retain fine grained predominately silt tailing. The initial cells were designed to contain 8 million tons. Three horizontal expansions and numerous staged raises have been made to the initial facility bringing the planned storage to 150 million tons at a height of 225 feet. Currently additional expansions are being considered. The initial stages of each basin were constructed as downstream embankments and the basins of each initial stage were lined with a 12-inch thick layer of low permeability soils overlain by a 12-inch thick drain layer containing a series of corrugated, slotted HDPE drain pipes. A drain/transition layer was included in the upstream face of the raises so that the fine-grained tailing did not migrate into the rock fill and any seepage was contained within the upstream side of the initial lined embankment where it was collected in the lined basin. Thus, no lining was needed above the initial embankment. This paper discusses the design, construction and operation of the facility including a summary of the benefits realized by the type of embankment constructed and the use of rotational, thin layered, air dried deposition. The features discussed could be considered for inclusion in other projects to provide safety and security, reduce costs and provide efficient operations.

 

Download the full technical paper.

Download

Perspectivas recientes

Febrero 2024
Empoderamiento y Resiliencia
Enero 2024
Balancing Act: Water Usage Management Vital for a Sustainable Future
Enero 2024
A Difficult Balance Between Engineering, Environmental, Social and Economic Aspects
Noviembre 2023
Knight Piésold Commences with the ESIA for Haib Copper
Noviembre 2023
Insights from the Compilation and Critical Assessment of Breach and Runout Characteristics from Historical Tailings Dam Failures: Implications for Numerical Modelling
Noviembre 2023
Earthquake-induced Deformation Analysis of a TSF Undergoing Tailings Reprocessing
Noviembre 2023
Case Study: Approach to Determining the Risk Mitigation Priority of a Historic TSF in North America
Octubre 2023
Data Management and Insights for Effective Tailings Storage Facility Management
Octubre 2023
The Role of Sensitivity Analysis in Selecting Dam Breach Parameters
Octubre 2023
Influence of Increased Confining Stress on Undrained Behavior of Tailings: A Case History at the Candelaria Mine
Octubre 2023
The Re-use of Existing Bituminous Stabilised Materials for the Rehabilitation of National Route 7 - Case Study
Septiembre 2023
Transición energética para gerentes de mina
Agosto 2023
Interview: Guillermo Barreda, Gerente General, Knight Piésold Perú
Julio 2023
Selection of Soil Shear Strength Parameters Based on Integrated In Situ Tests, Lab Tests and Numerical Calibration Approach
Junio 2023
Leveraging Knowledge and Experience of a Well-Formed Independent Tailings Review Board to Enhance Tailings Facility Safety
Mayo 2023
Is the Implementation of Dry Stacking for Tailings Storage Increasing? A Southern African Perspective
Febrero 2023
Canadian Consulting Engineer's Lifetime Achievement Awards: Jeremy Haile
Febrero 2023
Geotechnical Characterization of Collapsible Salty Sands Subjected to Monotonic and Cyclic Loadings – A Case Study for Areas with High Seismicity
Noviembre 2022
Application of the 3D Limit Equilibrium Method in Tailings Dam Breach Analysis
Noviembre 2022
Evaluation of Tailings Behaviour for Dam Breach Assessment