Investigation of Sediment Transport Through a Run-of-River Hydroelectric Project

Investigation of Sediment Transport Through a Run-of-River Hydroelectric Project

Author: Violeta Martin, Michael Pullinger, Alana Shewan, Nathan Smith
Conference: HydroVision International 2014
Date: July 22-25, 2014

A 25 MW run-of-river hydroelectric project is proposed in coastal British Columbia, Canada. Baseline studies identified that the bedload sediment transport rate in the project area is relatively low, and consequently, interruption of bed material replenishment in the reaches downstream of the intake represents an environmental concern.

A prerequisite for the successful design of the proposed project includes passing of the spawning size gravel through the intake facility during the period of headpond sediment infilling. A sluice gate has been incorporated in the intake structure to enable the sluicing of sediment. Numerical modelling was undertaken to aid with the intake design and to determine the sediment transport efficiency through the headpond. Hydrodynamic modelling techniques (1D, 2D and CFD) were combined to assess the proposed design and provide an overview of water depths, velocities and bed shear stresses along with the potential for gravel mobility through the headpond reach both before and after the construction of the intake.

 

Download the full technical paper.

Download

Perspectivas recientes

Abril 2024
Synthetic Rock Mass Modeling of Progressive Unravelling and Overall Slope Stability Using the Discrete Element Method
Abril 2024
Operational Slope Stability Risk Management for Large Open Pits at the Mount Milligan Mine – A Case Study
Febrero 2024
Empoderamiento y Resiliencia
Enero 2024
Balancing Act: Water Usage Management Vital for a Sustainable Future
Enero 2024
A Difficult Balance Between Engineering, Environmental, Social and Economic Aspects
Noviembre 2023
Knight Piésold Commences with the ESIA for Haib Copper
Noviembre 2023
Insights from the Compilation and Critical Assessment of Breach and Runout Characteristics from Historical Tailings Dam Failures: Implications for Numerical Modelling
Noviembre 2023
Earthquake-induced Deformation Analysis of a TSF Undergoing Tailings Reprocessing
Noviembre 2023
Case Study: Approach to Determining the Risk Mitigation Priority of a Historic TSF in North America
Octubre 2023
Data Management and Insights for Effective Tailings Storage Facility Management
Octubre 2023
The Role of Sensitivity Analysis in Selecting Dam Breach Parameters
Octubre 2023
Influence of Increased Confining Stress on Undrained Behavior of Tailings: A Case History at the Candelaria Mine
Octubre 2023
The Re-use of Existing Bituminous Stabilised Materials for the Rehabilitation of National Route 7 - Case Study
Septiembre 2023
Transición energética para gerentes de mina
Agosto 2023
Interview: Guillermo Barreda, Gerente General, Knight Piésold Perú
Julio 2023
Selection of Soil Shear Strength Parameters Based on Integrated In Situ Tests, Lab Tests and Numerical Calibration Approach
Junio 2023
Leveraging Knowledge and Experience of a Well-Formed Independent Tailings Review Board to Enhance Tailings Facility Safety
Mayo 2023
Is the Implementation of Dry Stacking for Tailings Storage Increasing? A Southern African Perspective
Febrero 2023
Canadian Consulting Engineer's Lifetime Achievement Awards: Jeremy Haile
Febrero 2023
Geotechnical Characterization of Collapsible Salty Sands Subjected to Monotonic and Cyclic Loadings – A Case Study for Areas with High Seismicity