Landslide Risk Management for the Construction and Operation of the Upper Lillooet River Hydroelectric Facility Near Pemberton, BC

Landslide Risk Management for the Construction and Operation of the Upper Lillooet River Hydroelectric Facility Near Pemberton, BC

Author: James Haley, Pierre Friele
Conference: Geohazards 7
Date: June 3-6, 2018

ABSTRACT
The Upper Lillooet River Hydroelectric Facility is situated approximately 60 km northwest of Pemberton in southwest British Columbia, Canada. The site is located on the north side of the Mount Meager Volcanic Complex (MMVC), which comprises weak, locally hydrothermally altered rocks and is especially prone to large (>1 Mm3) landslides.

Landslide risk management plans were developed for both the construction and operational phases of the project. Under the framework of the landslide risk management plans, the work areas at the site were assigned one of three hazard ratings (Low, Moderate or High). The ratings reflect the return-frequency and magnitude of landside that would be anticipated to affect the work area. A risk analysis was completed taking account of the predicted workforce requirements for each work area and the vulnerability of individuals to the hazards. The landslide hazard from the MMVC is seasonal and conditioned by weather. Four hazard alert levels were defined based on rainfall and temperature criteria. Risk mitigation requirements for each work area were determined with respect to the different hazard alert levels. In moderate and high risk areas, the key mitigation measures implemented at elevated alert levels were the use of a ‘spotter’, restricting access and temporarily implementing ‘Shutdown’ of work. Rainfall and temperature were continually monitored during construction using an on-site climate station, and the mitigation measures were varied accordingly.

The landslide risk was exacerbated when, in the summer of 2015, the area was affected by a wildfire. Rock fall and boulder fall hazards were mitigated by undertaking scaling work and constructing a protection berm, and enhanced ‘Shutdown’ procedures were implemented. The management plan for the operational phase of the project incorporates a full Quantitative Risk Assessment for each work area and work activity with respect to Personal Individual Risk. The risk was evaluated against a threshold risk tolerance criteria of 1:10,000 per annum to verify the mitigation requirements.

 

Download the full technical paper.

Download

Perspectivas recientes

Febrero 2024
Empoderamiento y Resiliencia
Enero 2024
Balancing Act: Water Usage Management Vital for a Sustainable Future
Enero 2024
A Difficult Balance Between Engineering, Environmental, Social and Economic Aspects
Noviembre 2023
Knight Piésold Commences with the ESIA for Haib Copper
Noviembre 2023
Insights from the Compilation and Critical Assessment of Breach and Runout Characteristics from Historical Tailings Dam Failures: Implications for Numerical Modelling
Noviembre 2023
Earthquake-induced Deformation Analysis of a TSF Undergoing Tailings Reprocessing
Noviembre 2023
Case Study: Approach to Determining the Risk Mitigation Priority of a Historic TSF in North America
Octubre 2023
Data Management and Insights for Effective Tailings Storage Facility Management
Octubre 2023
The Role of Sensitivity Analysis in Selecting Dam Breach Parameters
Octubre 2023
Influence of Increased Confining Stress on Undrained Behavior of Tailings: A Case History at the Candelaria Mine
Octubre 2023
The Re-use of Existing Bituminous Stabilised Materials for the Rehabilitation of National Route 7 - Case Study
Septiembre 2023
Transición energética para gerentes de mina
Agosto 2023
Interview: Guillermo Barreda, Gerente General, Knight Piésold Perú
Julio 2023
Selection of Soil Shear Strength Parameters Based on Integrated In Situ Tests, Lab Tests and Numerical Calibration Approach
Junio 2023
Leveraging Knowledge and Experience of a Well-Formed Independent Tailings Review Board to Enhance Tailings Facility Safety
Mayo 2023
Is the Implementation of Dry Stacking for Tailings Storage Increasing? A Southern African Perspective
Febrero 2023
Canadian Consulting Engineer's Lifetime Achievement Awards: Jeremy Haile
Febrero 2023
Geotechnical Characterization of Collapsible Salty Sands Subjected to Monotonic and Cyclic Loadings – A Case Study for Areas with High Seismicity
Noviembre 2022
Application of the 3D Limit Equilibrium Method in Tailings Dam Breach Analysis
Noviembre 2022
Evaluation of Tailings Behaviour for Dam Breach Assessment