ENVIRONMENTAL IMPACT ASSESSMENT (EIA) FOR THE PROPOSED DEVELOPMENT OF THE HAIB COPPER MINE NEAR NOORDOEWER, //KHARAS REGION, NAMIBIA

MEFT Application Number: APP-006117

Name of Applicant: Haib Minerals (Pty) Ltd as subsidiary of Koryx Copper

Environmental Assessment Practitioner (EAP): Knight Piésold Consulting (Namibia) (Pty) Ltd (KP)

Nature and location of proposed activities: Located approximately 25 km north-east of Noordoewer, along Namibia’s southern border. The proposed activities include: 

  • An open-pit copper mine,
  • On-site processing plant,
  • Tailings and waste storage facilities,
  • Solar photovoltaic (PV) plant,
  • Off-Channel Storage Dam, and associated pipeline and booster pump stations,
  • Access roads,
  • Power supply lines and
  • Supporting infrastructure

If approved, construction will take 2–3 years, with a mine life of approximately 33 years. 

 

 

PROJECT LOCATION

GPS Coordinates: -28.686438° ; 17.879938° 

Location of the proposed developments associated with Exclusive Prospecting License (EPL) 3140 (See below)

 
DOCUMENT AVAILABILITY

The Environmental Impact Assessment (EIA) and Environmental Management Plan (EMP) for the Proposed Haib Copper Mine Activities are available.

 

Click to download 

Available Project Information 

 

REGISTRATION AS AN I&AP

To register as an Interested and Affected Party (I&AP), please provide your name, contact details and comments to the contact below:

Contact: Heidri Nel 
Mobile/WhatsApp: +26 48 165 17336  (08:00- 16:00)  
Email: ESIAHaib@udanam.com

Note if you are registered as an I&AP for the Koryx application you will automatically be registered for the NamWater Application 

 
For more information, please contact the following: 
  • EAP: Joseph Mulders 
  • Mobile/WhatsApp: +27 72 754 2603

 

  • EAP: Lima Maartens 
  • Landline: +264 61 255750 

 

  • Support: Bianca Eiases 
  • Landline: +264 61 307297 

 -

 

EIA REGULATORY PROCESS TO DATE 

The EIA regulatory process is in accordance with the Environmental Management Act, 7 of 2007 and the EIA Regulations

Phase Purpose/Progress Application Focus
Screening

1. Application of ECC to MIME and MEFT - July 2025

2. Screening Notice provided by MEFT- July 2025

Haib Copper Project
Scoping (Defining the ToR)

3. I&AP Identification and Notification- July/August 2025

4. Public Consultations- August 2025

5. Determine ToR for EIA and included in draft Scoping Report- September 2025

6. I&AP review on draft Scoping Report- September to November 2025

Haib Copper Project
NamWater included as the proponent of water related activities thus splitting the application into two separate applications- January 2026. Note as the activities did not change the ToR for Haib Copper Project EIA remained valid moving forward.
Impact Reporting (EIA) & Environmental Management Plan (EMP)

7. Assessment of alternatives, undertake/update specialist studies, draft EIA and EMP- November 2025 to April 2026

8. Notification- March/April 2026

9. Public consultations- April 2026

10. Update EIA - 19 July 2026

11. I&AP Review and Comment – 20 July to 12 August 2026

12. Finalise EIA and submit Application package- 21 August 2026   

 

Haib Copper Mine
Decision Making 13. Authority assessment and decision by CA - PENDING Haib Copper Mine
Appeal 14. EAP to notify registered I&APs of decision and rights to appeal- PENDING  Haib Copper Mine