Case Study: Approach to Determining the Risk Mitigation Priority of a Historic TSF in North America

Case Study: Approach to Determining the Risk Mitigation Priority of a Historic TSF in North America

Authors: Andy Rudy, Jeff Coffin
Conference: Tailings and Mine Waste 2023
Date: November 5-8, 2023

ABSTRACT

Following an exploratory site investigation campaign consisting of more than twenty sections on a series of historic tailings dams, it was clear that many, if not all, of the historic cells would require some type of risk mitigation. Over the facility’s long history, the tailings basin had been divided into cells, some of which were partially closed while others were receiving new tailings. All the cells had been constructed using the upstream method, with some cells showing interbedded layers of potentially contractive material.

A series of buttresses were proposed for the site; however, the buttressing project was extensive enough that it required annual construction for up to five years. Furthermore, portions of the historic dam were located directly adjacent to other infrastructure – so close, in fact, that a buttress in those areas was considered unfeasible. As such, a combination of tailings reprocessing, dam deconstruction, and buttressing was proposed to mitigate the risks on site.

These mitigations were proposed in phases, beginning with the highest risk facility. The highest risk facility was determined based on a series of seven parameters. Six of these were geotechnical parameters, and the seventh was a parameter to measure the unknowns remaining in the site investigation at the time.

The geotechnical parameters were the Average Cyclic Resistance Ratio (CRR), the Normalized Shear Wave Velocity (Vs1), the Average State Parameters, the geometric design parameters (called the Geometric Product), the Undrained Factor of Safety at Residual Strength, and the Presence of a Pond of Fresh Tailings in the Impoundment. These factors, along with a two-day risk assessment workshop, were used to prioritize the risk mitigation campaign and target areas for further investigation. This case study will show the approach to prioritizing and mitigating these risks.

 

Download the full paper.

Download

Recent Insights

April 2024
Synthetic Rock Mass Modeling of Progressive Unravelling and Overall Slope Stability Using the Discrete Element Method
April 2024
Operational Slope Stability Risk Management for Large Open Pits at the Mount Milligan Mine – A Case Study
April 2024
Risk and Informed Approach to TSF Design and Operation
February 2024
Empowerment and Resilience
January 2024
Balancing Act: Water Usage Management Vital for a Sustainable Future
January 2024
A Difficult Balance Between Engineering, Environmental, Social and Economic Aspects
November 2023
Knight Piésold Commences with the ESIA for Haib Copper
November 2023
Insights from the Compilation and Critical Assessment of Breach and Runout Characteristics from Historical Tailings Dam Failures: Implications for Numerical Modelling
November 2023
Earthquake-induced Deformation Analysis of a TSF Undergoing Tailings Reprocessing
October 2023
Data Management and Insights for Effective Tailings Storage Facility Management
October 2023
The Role of Sensitivity Analysis in Selecting Dam Breach Parameters
October 2023
Influence of Increased Confining Stress on Undrained Behavior of Tailings: A Case History at the Candelaria Mine
October 2023
The Re-use of Existing Bituminous Stabilised Materials for the Rehabilitation of National Route 7 - Case Study
September 2023
Transición energética para gerentes de mina
August 2023
Interview: Guillermo Barreda, Gerente General, Knight Piésold Perú
July 2023
Selection of Soil Shear Strength Parameters Based on Integrated In Situ Tests, Lab Tests and Numerical Calibration Approach
June 2023
Leveraging Knowledge and Experience of a Well-Formed Independent Tailings Review Board to Enhance Tailings Facility Safety
May 2023
Is the Implementation of Dry Stacking for Tailings Storage Increasing? A Southern African Perspective
February 2023
Canadian Consulting Engineer's Lifetime Achievement Awards: Jeremy Haile