Risk Mitigation through Design Optimization Utilizing Seasonal Effects under Arctic Conditions at the Amaruq Mine

Risk Mitigation through Design Optimization Utilizing Seasonal Effects under Arctic Conditions at the Amaruq Mine

Authors: Christian Tremblay1, Ben Peacock2, Véronique Falmagne3, K.S. Kalenchuk4, Erik Bellefleur5
Conference: Slope Stability 2024
Date: April 14-19, 2024

1 Agnico Eagle Mines Limited, North Bay, Canada
2 Knight Piésold Ltd., North Bay, Canada
3 Agnico Eagle Mines Limited, Rouyn-Noranda, Canada
4 RockEng Inc., Kingston, Canada
5 Agnico Eagle Mines Limited, Baker Lake, Canada

ABSTRACT

Agnico Eagle Mines is currently operating the Amaruq Mine located in the Canadian Arctic. Since the beginning of the open pit operations, a series of bench-scale failures and rockfalls have occurred during the freshet and summer months (May to September). These instabilities can be correlated with a prominent and very weak komatiite unit. The komatiite is an ultramafic rock commonly altered to a chlorite carbonate shist. The domain is strongly anisotropic and rock mass competency is highly variable. High strain zones within the komatiite, which are identified in core as zones of low RQD, with shearing or gouge are impacting the slope performance locally.

This paper presents the geological and geotechnical site characterization, emphasizing the challenging komatiite conditions including the impact of the high-strain structures. An overview of the historic slope performance and failure mechanisms is provided, with focus on the influence of the seasonal effect and how the mine plan has been adjusted to take advantage of more favorable frozen conditions. The evolution of the pit slope design in response to kinematic analyses and numerical modelling is presented as well as the strategic design updates and tactical measures implemented to mitigate risk through the life of mine.

 

Download the full paper.

Download

Perspectivas recientes

Junio 2025
The Essence of Material Compatibility in Advanced Barrier Systems of Existing TSFs
Junio 2025
Inverted Barriers in Tailings Storage Facilities: Lessons Learnt
Junio 2025
Prioritizing the Mitigation of Legacy Geomechanical Mine Hazards Using a Risk-Based Approach
Mayo 2025
Knight Piésold: Sustainable Projects in DRC Through Baseline Studies
Abril 2025
Advancements in Geotechnical Investigations for the Characterisation of Upstream Tailings Dams in SA
Noviembre 2024
Design of a Co-disposal Facility for Thickened Tailings and Potentially Acid-generating Waste Rock
Noviembre 2024
Compaction Sensitivity in Tailings Stack Infiltration Modeling: Unsaturated Properties Uncertainty Analysis
Noviembre 2024
Volumes of Dam Material Mobilized by Erosion During Tailings Dam Failure Events
Octubre 2024
Estudio de rotura de una presa de jales en la zona centro-norte de México
Septiembre 2024
Grouting to Reduce Seepage at Neckartal Dam, Namibia
Septiembre 2024
Influence of Pre-Existing Mobilized Zones on B3 Cave Propagation and Initial Subsidence at the New Afton Mine
Septiembre 2024
Importance of Indigenous Community Engagement related to ARD/ML and Long-Term Water Quality
Septiembre 2024
Effective Assessment of ARD/ML Potential for Non-Mining Infrastructure Projects
Agosto 2024
CESA Aon Engineering Excellence Awards 2024: Kikagati Hydropower Plant
Julio 2024
Interview: Mario Lazo Emparanza, Regional Manager, Knight Piésold Chile
Julio 2024
A Diverse Approach in Geosynthetic Barrier Systems to Ensure Environmental Compliance of Existing TSFs
Julio 2024
Case History: Application Of Geosynthetics in A Tailings Storage Facility Rockfill Buttress Construction Project
Julio 2024
Visionary Leadership: Driving Engineering Excellence in Africa with Vishal Haripersad
Junio 2024
Concept Feasibility and Predicted Behavior of Mining a Rock Tower with Drill-and-Blast Undermining Using Dynamic Three-Dimensional Discontinuum Numerical Models
Junio 2024
Estimating Shear Stress within a Clay Foundation Using the Burgers-Creep Model