Mount Polley Tailings Dam Failure - More Lessons to Learn

Mount Polley Tailings Dam Failure - More Lessons to Learn

Author: Ken J. Brouwer, Greg L. Smyth 
Conference: CIM 2017 Convention
Date: April 30-May 3, 2017

ABSTRACT
The Mount Polley Tailings Facility was first constructed in 1996 at a time when three new mines were under development in BC, Canada (Mount Polley, Huckleberry and Kemess South). The design, review and regulatory oversight of these three projects were influenced by tailings facility failures that had occurred at that time (Merriespruit, South Africa (1994), Omai, Guyana (1995)). Qualified geotechnical engineers developed designs, Independent  ngineering Reviews were conducted, and enforcement of mining regulations occurred with strong participation by the Provincial Government. The concurrent development of these mines allowed for lessons learned from one project to be applied to the others. For example, foundation instability in glaciolacustrine soils encountered during construction of the starter dam at the Kemess Tailings Facility resulted in review of similar glaciolacustrine soils at the Mount Polley Tailings Facility, and the early embankment designs incorporated suitably flat and/or buttressed slopes to accommodate the potentially weak foundation conditions. The Mount Polley dam failure occurred after the facility design was modified by incorporating steeper overall slopes for the higher embankments. Recent regulatory changes in BC mandate Independent Review Boards along with increased inspections by Regulators for tailings facilities. This will result in more conservative designs with increased oversight during all phases of mine operations, in order to foster a safer mining industry.

 

Download the full technical paper.

Download

Recent Insights

February 2024
Empowerment and Resilience
January 2024
Balancing Act: Water Usage Management Vital for a Sustainable Future
January 2024
A Difficult Balance Between Engineering, Environmental, Social and Economic Aspects
November 2023
Knight Piésold Commences with the ESIA for Haib Copper
November 2023
Insights from the Compilation and Critical Assessment of Breach and Runout Characteristics from Historical Tailings Dam Failures: Implications for Numerical Modelling
November 2023
Earthquake-induced Deformation Analysis of a TSF Undergoing Tailings Reprocessing
November 2023
Case Study: Approach to Determining the Risk Mitigation Priority of a Historic TSF in North America
October 2023
Data Management and Insights for Effective Tailings Storage Facility Management
October 2023
The Role of Sensitivity Analysis in Selecting Dam Breach Parameters
October 2023
Influence of Increased Confining Stress on Undrained Behavior of Tailings: A Case History at the Candelaria Mine
October 2023
The Re-use of Existing Bituminous Stabilised Materials for the Rehabilitation of National Route 7 - Case Study
September 2023
Transición energética para gerentes de mina
August 2023
Interview: Guillermo Barreda, Gerente General, Knight Piésold Perú
July 2023
Selection of Soil Shear Strength Parameters Based on Integrated In Situ Tests, Lab Tests and Numerical Calibration Approach
June 2023
Leveraging Knowledge and Experience of a Well-Formed Independent Tailings Review Board to Enhance Tailings Facility Safety
May 2023
Is the Implementation of Dry Stacking for Tailings Storage Increasing? A Southern African Perspective
February 2023
Canadian Consulting Engineer's Lifetime Achievement Awards: Jeremy Haile
February 2023
Geotechnical Characterization of Collapsible Salty Sands Subjected to Monotonic and Cyclic Loadings – A Case Study for Areas with High Seismicity
November 2022
Application of the 3D Limit Equilibrium Method in Tailings Dam Breach Analysis
November 2022
Evaluation of Tailings Behaviour for Dam Breach Assessments