Klamath River Renewal Project - Dam Breach Analysis Used for Designing the Final Breach of the Iron Gate Dam

Klamath River Renewal Project - Dam Breach Analysis Used for Designing the Final Breach of the Iron Gate Dam

Authors: Daniel Adria1, Violeta Martin1, Nick Rong1, Katrina Wechselberger1
Conference: CDA 2025 Annual Conference and Trade Show
Date: September 29 - October 1, 2025

1 Knight Piesold Ltd., Vancouver, BC, Canada

ABSTRACT

The Iron Gate Dam (IGD) is the most downstream dam of the four facilities of the Klamath River Renewal Project (Nistor et al. 2025). It was partially removed with conventional deconstruction techniques. Due to site and drawdown schedule constraints, the final remaining portion of the IGD had to be breached with a head difference of approximately 23 ft (7 m). The assessment of the planned breach and the final IGD reservoir release is presented in this paper. The range of peak outflows during the intentional breach phase was assessed for variable inflow conditions with the goal to establish the most sensitive and limiting breach parameters for safe final breaching and reservoir release. The design of the breach plug and breach channel through the remaining IGD dam incorporated the findings from the breach analysis and included a predefined cross sectional geometry and placed riprap, with the goal to have a peak breach outflow within the allowable flow limits. The final breach was initiated on August 28, 2024. The breach plug slowly eroded, requiring encouragement from long-arm excavators. The full river flow was discharging through the breach by the end of the day. The peak discharge recorded at the USGS gage downstream of Iron Gate Dam was well within the allowable flow limits. Overall, the planned breach was successful due to the breach analysis completed in the design phase.

 

Download the full paper.

Download

Recent Insights

November 2025
Case Study: Assessing Construction-Induced Deformations in Tailings Storage Facility Embankments
November 2025
Geotechnical Characterization of Cyclone Underflow Tailings under High Confining Pressures
October 2025
2025 CCE Awards Showcase: Salton Sea Species Conservation Habitat Project
September 2025
Klamath River Renewal Project - Optimization of the Iron Gate Dam Historic Diversion Tunnel Using CFD Analysis to Support Reservoir Drawdown
September 2025
Klamath River Renewal Project - Design of Dam Modification for Reservoir Drawdown, River Diversion and Dam Removal of the Copco No. 1 Dam
September 2025
Klamath River Renewal Project
September 2025
Drawdown Modelling of Four Reservoirs on the Klamath River to Support Hydroelectric Facility Decommissioning
September 2025
Laying Groundwork for Future Mining: Infrastructure Support by Knight Piésold
September 2025
Lessons Learned in the Interpretation of SCPT on a Tailings Facility Using the CSSM Framework
September 2025
Challenges of Tailings Transport Pumping Systems in Negative Static Head Applications
September 2025
Hydraulic Evaluation of Tailings Transport Systems in Mountainous Terrain: Density Wave Analysis
September 2025
The Role of Rheology Tests in the Design and Operation of Long-Distance Slurry Transport Systems
August 2025
The Evolution of Structural Domains from Scoping Study to Operations for the Meadowbank Mine – Amaruq Site
August 2025
Safe Dams, Straight Talk: The Knight Piésold Difference
July 2025
Knight Piésold Zambia: Building a Future of Engineering Brilliance and Local Empowerment
July 2025
Water Engineering for Modern Mining: Bridging Mining with Sustainability
June 2025
The Essence of Material Compatibility in Advanced Barrier Systems of Existing TSFs
June 2025
Inverted Barriers in Tailings Storage Facilities: Lessons Learnt
June 2025
Prioritizing the Mitigation of Legacy Geomechanical Mine Hazards Using a Risk-Based Approach