A Brief History of the RCC at Neckartal Dam

A Brief History of the RCC at Neckartal Dam

Author: Edwin Lillie, Elvin Pesch, Louis Barnard
Conference: SANCOLD Annual Conference and AGM 2018
Date: November 7-9, 2018

ABSTRACT
The construction of Neckartal Dam started in September 2013. The full-scale trial section was done in August 2015 and the first RCC was placed on the dam foundation in October 2015. The RCC placement was completed 32 months later in May 2018. This paper gives a brief history of the RCC through the various project phases. Two mixes were used, a 20/38 high cementitious mix for an impermeable zone (Zone 1) in the upstream face of the dam and two 10/38 low cementitious mixes for the main body of the dam (Zone 2). The Contractor produced a total of 3.12 million tons of aggregate for the project over 33 months at an average of 94 800 tons per month. The overall crushing plant efficiency over the 33 months of production was 33%. The Contractor produced a total of 836 000m3 of RCC for the project over 32 months at an average rate of 26 127m3 per month. The overall plant efficiency over the 32 months was 17%. Over the whole RCC placement period, there were interruptions for many reasons, some within the Contractor’s control such as plant breakdowns, insufficient sand, cement and/or fly ash, waiting for shutters to be moved, preparing RCC surfaces, sequencing of the intake tower construction etc. There were also some delays beyond the Contractor’s control such as strikes, break downs and late payments. The RCC cube tests indicated that the set RCC easily achieved the strength requirements of the project specification of 20MPa at 365 days for Zone 1 and 10MPa at 365 days for Zone 2.

 

Download the full technical paper.

Download

Recent Insights

February 2024
Empowerment and Resilience
January 2024
Balancing Act: Water Usage Management Vital for a Sustainable Future
January 2024
A Difficult Balance Between Engineering, Environmental, Social and Economic Aspects
November 2023
Knight Piésold Commences with the ESIA for Haib Copper
November 2023
Insights from the Compilation and Critical Assessment of Breach and Runout Characteristics from Historical Tailings Dam Failures: Implications for Numerical Modelling
November 2023
Earthquake-induced Deformation Analysis of a TSF Undergoing Tailings Reprocessing
November 2023
Case Study: Approach to Determining the Risk Mitigation Priority of a Historic TSF in North America
October 2023
Data Management and Insights for Effective Tailings Storage Facility Management
October 2023
The Role of Sensitivity Analysis in Selecting Dam Breach Parameters
October 2023
Influence of Increased Confining Stress on Undrained Behavior of Tailings: A Case History at the Candelaria Mine
October 2023
The Re-use of Existing Bituminous Stabilised Materials for the Rehabilitation of National Route 7 - Case Study
September 2023
Transición energética para gerentes de mina
August 2023
Interview: Guillermo Barreda, Gerente General, Knight Piésold Perú
July 2023
Selection of Soil Shear Strength Parameters Based on Integrated In Situ Tests, Lab Tests and Numerical Calibration Approach
June 2023
Leveraging Knowledge and Experience of a Well-Formed Independent Tailings Review Board to Enhance Tailings Facility Safety
May 2023
Is the Implementation of Dry Stacking for Tailings Storage Increasing? A Southern African Perspective
February 2023
Canadian Consulting Engineer's Lifetime Achievement Awards: Jeremy Haile
February 2023
Geotechnical Characterization of Collapsible Salty Sands Subjected to Monotonic and Cyclic Loadings – A Case Study for Areas with High Seismicity
November 2022
Application of the 3D Limit Equilibrium Method in Tailings Dam Breach Analysis
November 2022
Evaluation of Tailings Behaviour for Dam Breach Assessments