Award of Excellence: Kokish River Hydroelectric Project

Award of Excellence: Kokish River Hydroelectric Project

Publication: Canadian Consulting Engineer
Issue: October/November 2015
Issue Title: 2015 Canadian Consulting Engineering Awards

The Kokish River Hydroelectric Project is a 45 MW run-of-river facility 15 km east of Port McNeill, on the north of Vancouver Island, B.C. Every step during the development process took into consideration the diversity of fish habitats in Kokish River. The project has unique and innovative details throughout the diversion reach designed to cater to this sensitive environment, and in particular the presence of steelhead trout and salmon. It has one of the largest capacity Coanda screen intakes in the world, together with one of the smallest Obermeyer crest gates in the world, a wrap-around vertical slot fish ladder, and a tailrace fish screen.

As the lead design engineer, Knight Piésold worked closely with the owner, Kwagis Power Limited Partnership, and the EPC Contractor, Peter Kiewit Infrastructure, to develop innovative and cost-effective solutions that more than met the stringent fisheries permitting requirements. The Knight Piésold team was involved throughout the project’s development.

“Fish first” design
The intake and diversion weir were designed to:

  • Divert a portion of the natural stream flow to the water conveyance system, while excluding large sediment and debris to limit damage to the pipe and turbine generating equipment.
  • Provide safe passage — for both adult and juvenile salmon and steelhead trout — past the intake and diversion weir, for upstream and downstream migration.
  • Allow for precise control and realtime flow monitoring of the in-stream flow release downstream of the intake to maintain the natural aquatic ecology. The required in-stream flow releases varied by season and month from 3.4 m3/s to 12 m3/s.
  • Allow passage of flood flows without damage to the structure.

The 9.3 km-long water conveyance system is unusually long for a high-head, run-of-river project in B.C. Its design had to be cost-effective, yet robust, because the penstock is exposed to hydraulic transient

 

Read the full article.

Online  or  Download

Recent Insights

February 2024
Empowerment and Resilience
January 2024
Balancing Act: Water Usage Management Vital for a Sustainable Future
January 2024
A Difficult Balance Between Engineering, Environmental, Social and Economic Aspects
November 2023
Knight Piésold Commences with the ESIA for Haib Copper
November 2023
Insights from the Compilation and Critical Assessment of Breach and Runout Characteristics from Historical Tailings Dam Failures: Implications for Numerical Modelling
November 2023
Earthquake-induced Deformation Analysis of a TSF Undergoing Tailings Reprocessing
November 2023
Case Study: Approach to Determining the Risk Mitigation Priority of a Historic TSF in North America
October 2023
Data Management and Insights for Effective Tailings Storage Facility Management
October 2023
The Role of Sensitivity Analysis in Selecting Dam Breach Parameters
October 2023
Influence of Increased Confining Stress on Undrained Behavior of Tailings: A Case History at the Candelaria Mine
October 2023
The Re-use of Existing Bituminous Stabilised Materials for the Rehabilitation of National Route 7 - Case Study
September 2023
Transición energética para gerentes de mina
August 2023
Interview: Guillermo Barreda, Gerente General, Knight Piésold Perú
July 2023
Selection of Soil Shear Strength Parameters Based on Integrated In Situ Tests, Lab Tests and Numerical Calibration Approach
June 2023
Leveraging Knowledge and Experience of a Well-Formed Independent Tailings Review Board to Enhance Tailings Facility Safety
May 2023
Is the Implementation of Dry Stacking for Tailings Storage Increasing? A Southern African Perspective
February 2023
Canadian Consulting Engineer's Lifetime Achievement Awards: Jeremy Haile
February 2023
Geotechnical Characterization of Collapsible Salty Sands Subjected to Monotonic and Cyclic Loadings – A Case Study for Areas with High Seismicity
November 2022
Application of the 3D Limit Equilibrium Method in Tailings Dam Breach Analysis
November 2022
Evaluation of Tailings Behaviour for Dam Breach Assessments